Projects

To Bid on Projects please visit City of Ogden Purchasing Homepage link for active bid opening.          Purchasing Homepage

FUNDED PROJECTS

April 2022

  • Replacement of Antiquated Airport Generator with Larger Capacity Generator
    • Schedule for Completion - April 2022
    • COMPLETED APRIL 2022
  • Replacement of Hangar 755 Roof
    • Out for Bids - March 2022
    • Construction - June 2022
    • Schedule for Completion - September 2022

November 2021

  • Repair Pilot Control Lighting System Multiple Level Light Intensity 
    • Installation - November 2021
    • Schedule for Completion - Mid-December 2021
    • COMPLETED MARCH 2022 

October 2021

  • Demolition of Hangar N-850
    • Out for Bids - October 2021
    • Demolition - Mid-January 2022 
    • Scheduled for Completion - March 2022
    • COMPLETED MARCH 2022

September 2021

  • Design of $2 Million Expansion of Airport Terminal
    • Design - September 2021 - February 2022
    • Out for RFQ for Construction Manager General Contractor - April 2022
    • Construction - June 2022
    • Schedule for Completion - October 2024Terminal Expansion CMGC RFP Appendix A_Page_1 Terminal Expansion CMGC RFP Appendix A_Page_5 Opens in new window

August 2021

  • Remodel of Restaurant in Terminal
    • Design - Completed August 2021
    • Out for Bids - September 2021
    • Construction - October 2021
    • Schedule for Completion - March 2021
    • COMPLETED APRIL 2022

July 2021

  • Demolition of Old Tower on Top of Terminal Building. 
    • COMPLETED AUGUST 2021

June 2021

  • Demolition of Hangars N-420, S-543, S-553. 
    • COMPLETED JUNE 2021
  • Construction of Fiber Optic Network Loop Around OGD Airport for Internet Access / Data Transmission.
    • Out for Bids - June 2021
    • Construction Started - August 2021
    • Scheduled for Completion - January 2022
    •  COMPLETED DECEMBER 2021 
  • Maintenance Complex & West Side of Airport Improvements - Grading / Cleanup; Utilities Upgrade; Creation of West Side Entrance.
    • Under Design - June 2021 - January 2022 See Diagram below 
    • Out for Bids - February 2022
    • Construction Start - May 2022
    • Schedule for Completion - December 2022
  • Construction of New Partial Parallel Taxiway Foxtrot, West of Approach End of Runway 17.
    • Design - December 2021 See Diagram below
    • Out for Bids - March 2022
    • Construction - May 2022
    • Schedule for Completion - December 2022

West Exhibit

June - Sept 2021 

OGD AIRPORT NORTH TIE-DOWN APRON RECONSTRUCTION, SCHEDULE II - COMPLETED DECEMBER 2021 

Granite Construction is scheduled to begin the second half of the North Tie-Down Apron Reconstruction on Tuesday June 1st, 2021. 

Phase One - June 1st - July 19th

The pavement will be removed airside of four hangars. Each of these hangar owners & users should make arrangements to not have aircraft access in or out of their hangars between June 1st and July 19th.

Affected Hangars - N-1302, the northmost bay only, Hangar N-1410, Hangar N-1460, and Hangar N-1504.

Phase Two - July 19th - August 3rd

Twenty one (21) hangars will lose the ability to get an aircraft from their hangar to the Runway & Taxiways. Each hangar owner or user will need to make arrangements to not have aircraft access in or out of their hangars between July 19th and August 23rd. 

Affected Hangars - Hangar N848, Hangar N-824, Hangars N-946, N-942, N-936, N-930, N-924, N-918, N-1038, N-1034, N-1028, N-1022, N-1016 & N-1010, Hangar N-916, Hangar N-1004, Hangar 1108, Hangar N-1116, Hangar N-1110, Hangar N-1204, and Hangar N-1302.

Additional time will be required to core the tie-down anchor points and to paint in the striping and the tie-down "T's". 

These dates represent the best estimates for each phase, but the actual times could vary somewhat. 

OGD North Apron Phasing Plan May 2021 (1) Opens in new window


Other Misc. Projects

  • Utah 99's Painting of Compass Rose
    • Outlining and Painting of 80 ft Compass Rose - May 2022